Commissioning (software)
2.7 Commissioning modes
Control Units CU240S
Operating Instructions (Compact), 04/2006, A5E00766042B AA
2-45
Parameter Action / Description (Factory setting: bold) Setting
3: Expert: For expert use only
P0010 = 30 Commissioning parameter*
0: Ready
1: Quick commissioning
2: Inverter
30: Factory setting, parameter transfer
95: Safety commissioning (for Safety-Integrated CUs only)
P0803 = 1 Transfer data to EEPROM
0: Disabled
1: Start OP transfer
2: Start MMC Transfer
While the download is active "bUSY" will be displayed on the OP and the inverter will not
react to any commands.
If the download has been completed successfully, P0010 and P0803 will be set to 0 and the
OP display will return to normal.
If the download has failed, F00055 (failure while saving parameter to EEPROM), F00057 (OP
fault) or F00058 (OP contents incompatible) will be displayed.
In this case attempt another download or perform a factory reset to allow the inverter to return
to a known state.
After a successful download the OP can be removed and inserted into another inverter for
download. Then perform the download steps again until the series commissioning has been
completed for all inverters.
2.7.9.3 Series commissioning with STARTER
Upload a parameter set with STARTER
Prerequisites
• An inverter with an apropriate parameter set is available (upload inverter)
• STARTER is installed on the PC used for series commissioning
• Supply voltage is active for the upload inverter
• The upload inverter is in "Ready State".
Connect the STARTER PC via the Option Port (USS on RS232, peer to peer) to the upload
inverter (PC connection Kit requiered), press the online button
and perform the upload by
activating the button
.
Note
Upload with STARTER to MMC
If you want to upload a parameter set with STARTER to an MMC, P0010, P0802 must be set
via the expert list.