Commissioning (software)
2.7 Commissioning modes
Control Units CU240S
2-30 Operating Instructions (Compact), 04/2006, A5E00766042B AA
2.7.8 Commissioning the application
2.7.8.1 Commissioning the application
Commissioning the application
After the motor - Inverter combination has been commissioned using quick commissioning,
the following parameters should be adapted and set according to the requirements of your
specific application. As an example, the following points should be considered:
Functional requirements of the inverter (for example, closed-loop process control with PID
controller)
Limit values
Dynamic requirements
Starting torques
Load surge requirement
Overload
Diagnostics.
If the application includes a function, which is not covered by the quick commissioning, then
the "Function" section in this manual or the parameter list should be consulted.
Note
In the factory setting, parameter changes are stored in the volatile memory of the inverter
(RAM). To safe the changes in the EEPROM one of the following methods can be used:
Set P0014 = 1 all changes stored immediately in the EEPROM
start data transfer from RAM to EEPROM via P0971 = 1 (when using OP) via
(with
STARTER).
The durartion of the data transfer depends on the number of changed parameters. In some
cases it can last several minutes.
With the OP data transfer is displayed with "bUSY".
When using STARTER it is displayed via a progress bar. The sucessful transfer is displayed
via a dialog box.