Commissioning
4.6 Data backup and standard commissioning
Inverter with CU240B-2 and CU240E-2 Control Units
86 Operating Instructions, 01/2011, FW 4.4, A5E02299792B AB
4.6.2 Backing up and transferring settings using STARTER
Backing up the inverter settings on PC/PG (upload)
1. Go online with STARTER: .
2. Click on the button "Load project to PG":
.
3. To save data in the PG (computer), click on
.
Transferring settings from the PC/PG into the inverter (download)
1. Go online with STARTER.
2. Click on the button "Load project to target system":
.
3. To save data in the converter, click on "Copy RAM to ROM"
.
Inverter with enabled safety functions
You must confirm the settings of the safety functions. Procedure:
1. In STARTER call-up the safety functions screen form
2. Click on the "Change settings" button
3. Click on the "Activate settings" button
4. Save your settings (copy RAM to ROM)
5. Switch off the inverter supply voltage
6. Wait until all LEDs on the inverter go dark. Now switch on the inverter supply voltage
again. Your settings only become effective after this power-on reset.