Siemens ISGS SG8158-00 User Manual Page 79

  • Download
  • Add to my manuals
  • Print
  • Page
    / 121
  • Table of contents
  • BOOKMARKS
  • Rated. / 5. Based on customer reviews
Page view 78
Appendix D: Acceptance Test Procedures
Siemens Energy & Automation, Inc. 73
Phase
ABC
Pickup LED illuminates.
Wisdom software records pickup in event log.
Return current to zero and reset timer.
Timing
5.
Apply appropriate value of current in reverse direction for the test. The results match Table D.5.
Pickup LED illuminates.
Display shows PICKUP 67 P12 (23, 31).
Wisdom software records pickup in event log.
6.
Relay times out per Table D.5
.
Trip LED illuminates.
Timer stops as Trip 1 contacts close.
Trip log indicates trip current value and time in pickup.
Wisdom software records trip on directional overcurrent.
Return current to zero and reset timer.
7. Remove control power from relay for five seconds, then restore it.
Trip LED re-illuminates after relay is powered up again.
8. Reset relay target.
Trip LED resets.
Repeat above steps for phase B-C and phase C-A; repeat the same steps also for Parameter Set B.
Testing may also be done for each phase at the user settings following the same procedure.
Table D.5 Test Points for Very Inverse Curve Characteristics
Multiple of Pickup Time Band 2 (seconds) Time Band 5 (seconds) Time Band 9.9 (seconds)
2X 3.73 9.30 18.38
4X 0.92 2.27 4.46
8X 0.40 0.96 1.87
Accuracy of the time curve for 2 I/Ip 20 is 5% from the defined value, or 30 ms, whichever is greater.
ISGS Acceptance Test
(continued)
Directional Phase Time Overcurrent (67) Function
(Phase-Neutral Connected VTs)
D
isv3o_1.bk : isv3otst.frm Page 73 Wednesday, August 7, 1996 10:51 AM
Page view 78
1 2 ... 74 75 76 77 78 79 80 81 82 83 84 ... 120 121

Comments to this Manuals

No comments